Sarnia and Western Intersection
Last week there was an on line presentation regarding the assessment of improvements at Western Road and Sarnia Road. You can review the presentation and the slides presented at https://getinvolved.london.ca/westernsarnia The next meeting, which will present the preferred option, will take place in the spring.

Metamora Storm Sewer Project
There have been some delays due to weather and rain. The City’s new plan is to wrap up the slope and outfall works by the end of this month and defer the roadworks (storm sewer, catch basins and curb work) until the spring. It’s never ideal to lay asphalt or concrete during cold months – you’ll see some temporary measures installed for the time being. Once the weather warms up in the spring, the crew will be back out on site for roughly 3 weeks to complete the rest of the work and address any deficiencies.
City staff will advise as to when replantings will take place and if the trail entrance will remain closed until all work is completed.