Construction of Western Road, Philip Aziz Avenue, and the intersection is planned to begin in May 2026 under the Phase 1 contract. Construction on Western Road, including the intersection, is anticipated to require one construction season targeting completion by the end of October 2026. Construction on Philip Aziz Avenue will require over one construction season, planned to be complete by approximately mid-2027.
Construction of the Sarnia Road walking and cycling infrastructure improvements will be completed under a separate Phase 2 contract planned to be completed in 2027 subject to property acquisition required to support the project.
There will be an open house prior to the start of the project location and date to be announced.

The Report to Infrastructure and Corporate Services Committee is available here.
Traffic Management and Communications
A traffic staging plan has been developed and is included in the construction plans. These plans balance mobility and access during all stages of construction while allowing the project to be completed in a timely and cost-effective manner. The following impacts and mitigations are anticipated during construction:
• Western Road from Platt’s Lane to Sarnia Road will be reduced to one lane in each direction during the construction in 2026.
• A full closure of the Western Road / Sarnia Road / Philip Aziz Avenue intersection will be required for up to two weeks to complete sewer and water connections. The closure is planned outside of the school year, when traffic volumes are anticipated to be lower.
• Philip Aziz Avenue will be closed for the duration of the project. Access to Alumni Stadium will be maintained via Huron Drive.
• Access to homes and businesses will be maintained.
• Construction activities will continue to be coordinated with Western University and London Transit Commission.
The traffic management plan will be communicated, monitored, and adjusted during construction based on traffic conditions.